View Full Version : Emergency Maintenance on Equnix Secaucus Core Switch


FH-Dave
11-01-2005, 03:42 PM
We will be rebooting our core switch in Equinix Secaucus data center in the next 15-30 minutes. The software on the core switch is being upgraded to its newer image version. This downtime should only last about 5-10 minutes or even less. Services/servers residing in the Equinix data center will be affected. Other services will not be affected.

All colocation and dedicated servers customers in Equinix will be affected. And the following will also be affected:

Shared Hosting customers:
- All mail servers
- CP Server
- MySQL2/PgSQL2 server
- Forums
- NS3

VPS customers:
- Hardware Node #5

Shared Hosting Reseller customers:
- none affected

We expect no complication due to this reboot. All services should resume normal within 5-10 minutes or even less.

FH-Dave
11-01-2005, 04:07 PM
The Switch has been sucessfully rebooted with its new software image version. Everything is back up and running normally now. Thank you!